Thursday, October 11, 2012

Wednesday, October 10, 2012

Plumbing Stub-Ups




The plumber has been working for the past couple of days making sure everything is in the correct spot.  He should be running water lines on Wednesday.  Hopefully I can get the electric installed in slab and be ready to pour by the end of the week.

Mr. Cleanup!


Waffle Slab




The slab is roughly on a 9' grid with 12W" x 32"D  beams.  Each of the beams will contain (2) post tension cables in the base and a slab tendon in the 5" slab.  Hopefully it will function similar to a boat and float on my clay filled soil.

Plumbing Layout



Finishing the Fill



Electric Line Extension








Working on extending my existing 200A service from my existing meter loop to the house.  I ran the conduit 2/3 of the way and am waiting for the slab pour to complete.